IEC61850 for Department of Sales in Xin Ya SS Substation
2020.10.16IEC61850 Power SCADA and IED Revamping Upgrade
![]() |
Department of Sales in Xin Ya SS Substation IEC61850 Power SCADA and IED Revamping Upgrade |
Taiwan - East Asia |
SS Medium Voltage |
Customer | Taiwan Power Company (Department of Sales in Xin Ya) |
Project start | February 2020 |
Project completion | November 2020 |
Products involved | SCADA System: ABB microSCADA (Redundant system) Gateway System: ABB microSCADA (Redundant system) IED(PMCC): ABB REF 620 *40 units IED(MCC): ZIV IRFA *15 units |
Number of data points | Up to 4,000 I/O points |
Protocols | DNP 3.0, IEC61850, IEEE1588 |
System structure | PRP |
Description of the project
Taiwan Power Company (TPC) was established on May 1st, 1946. It is a comprehensive power company covering with power generation, transmission, distribution and sales. It is the only electricity company that sell power in Taiwan. All electric power produced by private power plants and the cogeneration of gas and electricity must be sell to TPC, and TPC will resell to users.
This project began in February 2020, and applied SCADA System: ABB microSCADA (Redundant system), Gateway System: ABB microSCADA (Redundant system), 40 units of IED(PMCC): ABB REF 620, and 15 units of IED(MCC): ZIV IRFA. The project used IEC61850 system structure in the bay level and use DNP 3.0 transmit to the control center. There are total 3 control centers for this project.