IEC61850 for Department of Power Transmission of New built Feng Chou DS Substation
2020.12.25
IEC61850 for Department of Power Transmission
![]() |
Department of Power Transmission in Feng Chou DS Substation IEC61850 Power Transmission of New built |
Taiwan - East Asia |
DS High Voltage |
Customer | Taiwan Power Company (Department of Power Transmission in Feng Chou) |
Project start | May 2020 |
Project completion | October 2020 |
Products involved | SCADA System: ABB microSCADA (Redundant system) Gateway System: ABB microSCADA (Redundant system) IED(PMCC): ABB REF 620 *36 units IED(MCC): ZIV IRFA *9 units IED(MCC): ABB REF 620 *4 units |
Number of data points | Up to 4,000 I/O points |
Protocols | DNP 3.0, IEC61850, IEEE1588 |
System structure | PRP |
Description of the project
Taiwan Power Company (TPC) was established on May 1st, 1946. It is a comprehensive power company covering with power generation, transmission, distribution and sales. It is the only electricity company that sell power in Taiwan. All electric power produced by private power plants and the cogeneration of gas and electricity must be sell to TPC, and TPC will resell to users.
This project began in April 2020, and applied SCADA System: ABB microSCADA (Redundant system), Gateway System: ABB microSCADA (Redundant system), 36 units of IED(PMCC): ABB REF 620, and 9 units of IED(MCC): ZIV IRFA, 4units of IED(MCC)ABB REF620. The project used IEC61850 system structure in the bay level and use DNP 3.0 transmit to the control center. There are total 6 control centers for this project.